Expect delays on Rock Creek Road

Staff Writer

The second year of major reconstruction on the Rock Creek Road is underway. Work on this project began last year.
 Mono County requested the funding and the work is being completed on Mono County roads. The Federal Highway Administration has contracted and oversees the project that will improve the road, widen it, and provide a bicycle lane along a nine-mile stretch between the Rock Creek Pack Station and Crowley Lake Drive. Work this year is between the Rock Creek Pack Station to the lower end of the construction near Tom’s Place.
Here are important updates to the construction plan so that recreationists can plan their visit.
 Paving
Starting June 15, there will be no parking the last six miles of the construction area while they pave the road. Weekend work is necessary to complete this paving. In addition to 30 minute delays during the week, there will also be 30 minute delays on Friday, June 19, Saturday, June 20, and Friday June 26. Crews will not be working on Sunday, June 21. This paving will be completed on June 26.
Pulverizing
Starting June 22, there will be no parking on the lower three miles of construction while they pulverize the road.   
Bridge Slab Work: Four Hour Delays
As was announced earlier, there will be one week when there will four-hour delays twice per day while they are working on the bridges. This work is anticipated to start the week of July 6th and the closures are as follows:
July 7: 8 a.m.-noon and 1-5 p.m.
Wednesday July 8: 8 a.m.-noon and 1-5 p.m.
Thursday July 9th:  8 a.m.-noon and 1-5 p.m.
Friday July 10th:  8 a.m.-noon and 1-5 p.m. {only if needed}.
Equipment Mobilization
The contractor will be mobilizing equipment to the job site this weekend. There may be very short delays with flaggers as the transport vehicle gets into position to off load equipment.
Surveyors
Surveyors will also be working weekends the next few weeks but will not be stopping traffic.